Question: Question 2 ( 3 . 5 points ) Using the table, what is the latest start time for activity E ? table [ [

Question 2(3.5 points)
Using the table, what is the latest start time for activity E?
\table[[Activity,Predecessor,Time (days)],[A,--,8],[B,--,6],[C,--,3],[D,A,B,10],[E,C,8],[F,A,5],[G,D,E,3],[H,G,4]]
day 14
day 8
day 10
day 12
 Question 2(3.5 points) Using the table, what is the latest start