Question: Question 2 3 Every activity in a project network has various values that are calculated as the project's data is entered. Two of these values

Question 23
Every activity in a project network has various values that are calculated as the project's data is entered. Two of these values are
Total Slack and Free Slack. If Total Slack and Free Slack for an activity are equal, it means that
the activity is on the Critical Path
if slack is used, Total Slack and Free Slack will both be reduced and any Predecessor activity (or activities) will Not have their start delayed
if slack is used for the activity, Total Slack will be reduced by that amount, but Free Slack will remain unchanged
the activity is NOT on the critical path
if slack is used, Total Slack and Free Slack will both be reduced and any Successor activity (or activities) will Not have their start delayed
the start of any successor activity (or activities) will not be delayed as long as the Total and Free Slack values are greater than or equal to the
amount of slack used
if slack is used for the activity, Free Slack will be reduced, but Total Slack will not be reduced by the same amount
 Question 23 Every activity in a project network has various values

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!