Question: Question 2 8 ( 1 point ) What is the primary goal of fast tracking in project schedule optimization?To allocate additional resources to critical tasks.To
Question pointWhat is the primary goal of fast tracking in project schedule optimization?To allocate additional resources to critical tasks.To reduce the project's overall duration by overlapping or compressing tasks.To identify the critical path more accurately.To complete tasks as quickly as possible regardless of resource constraints.