Question: Question 2 : A partially solved PERT problem is detailed in the table below. Times are given in weeks. table [ [ Activity ]
Question :
A partially solved PERT problem is detailed in the table below. Times are given in weeks.
tableActivityAreceding Time,,ABACADAEBFBGC FHDIHJG I,KE J
Activity Preceding Optimistic Probable Pessimistic Expected Variance
tableTime,Time,Time,Time,ABACADAEBFBGC FHDIHJG I,KE J
a Draw the network diagram.
b Calculate the ES EF LS LF and Slack for each activity.
c Which activities form the critical path?
d What is the estimated time of the critical path?
e Calculate the expected time for each activity. Enter these values in the appropriate column in the table above.
f Given the variance for each activity, what are the project variance and the standard deviation?
g What is the probability of completion of the project before week
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
