Question: Question #2: For the Chairs BOM, represented in Question #1, the Master Production Schedule (MPS) is given as follows. The MPS is based on the
Question #2:
For the Chairs BOM, represented in Question #1, the Master Production Schedule (MPS) is given as follows. The MPS is based on the companys estimation of Chair demand for weeks 1 through 7.
MPS (includes GR)
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Chair | 0 | 0 | 0 | 100 | 225 | 0 | 45 |
Inventory Records
| Item | Description | SS | Lot Size Rule | LT | SR | OH |
| Chair | Independent demand | 40 | EOQ = 100 | 2 wks | 50 in week 3 | 50 |
| Chair | Independent demand | 40 | FOQ = 100 | 2 wks | 50 in week 3 | 50 |
- Do the MRP Calculations for Chair based on lot size rule of Economic Order Quantity (EOQ) = 100
Item: Chair SS= 40
Description: Independent Product Lot Size Rule: EOQ = 100
Level: 0 LT = 2 weeks
| Weeks |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| GR |
| 0 | 0 | 0 | 100 | 225 | 0 | 45 |
| SR |
|
|
| 50 |
|
|
|
|
| NR |
|
|
|
|
|
|
|
|
| OH | 50 |
|
|
|
|
|
|
|
| PORec |
|
|
|
|
|
|
|
|
| PORel |
|
|
|
|
|
|
|
|
- What is total inventory cost over 7 weeks based on the above material requirement plan, if ordering cost is $850 per order and holding cost is $10 per order? (hint: total inventory cost of 7 weeks is the sum of total order cost over 7 weeks and total holding cost over 7 weeks).
- Do the MRP Calculations for Chair based on lot size rule of Fixed Order Quantity (FOQ) = 100
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock