Question: Question 2: Software Installation Project S per Week Activity Immediate Predecessor Normal Cost Crash Cost Max reduction Normal Time (weeks) 5 8 10 Crash Time

Question 2: Software Installation Project S per

Question 2: Software Installation Project S per Week Activity Immediate Predecessor Normal Cost Crash Cost Max reduction Normal Time (weeks) 5 8 10 Crash Time (Weeks) 3 7 8 B A D A, B 3 4 3 E B $2,000 $5,000 $10,000 $3,000 $4,000 $8,000 $2,000 $6,000 $7,000 2 6 $4,000 $8,000 $12,000 $7,000 $5,000 $14,000 $2,000 $9,000 $15,000 F D 9 G H E, F G C, F 2 8 9 2 5 I 7 Penalty: $1000/ week beyond 25 weeks Indirect Project Costs: $ 2500 Per Week