Question: Question 2. Work on the capacity requirements problem: an assembly line comprises of three machines that work in a sequence as the diagram below: Construct
Question 2.
Work on the capacity requirements problem: an assembly line comprises of three machines that work in a sequence as the diagram below:

Construct the most efficient capacity requirement plan for fulfilling the demand for the products produced by this assembly line over four years: Year 1: 400 units, Year 2: 600 units, Year 3: 850 units, and Year 4: 1,150 units.
Each process comprises of several machines which run in parallel. Each of the machines for Process 1 has a capacity of 250 units / year, each machine for Process 2 has a capacity of 200 units / year, and each machine for Process 3 has a capacity of 250 units / year. Calculate the number of machines required for each process and the percentage of the utilisation of the machines for each year.