Question: Question 20 0.75 pts When using network diagrams for project management, the sequence of activities that has no slack time is called the A. Critical

Question 20 0.75 pts When using network diagrams

Question 20 0.75 pts When using network diagrams for project management, the sequence of activities that has no slack time is called the A. Critical Path B. Fast Lane C. Priority Trail D. Critical Sequence E. Acute Line