Question: Question 25 2 pts Calculate the earliest finish for Task Dif one of its predecessors, Task A, finishes on day 3, its other predecessor, Task

Question 25 2 pts Calculate the earliest finish
Question 25 2 pts Calculate the earliest finish for Task Dif one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task Dis 2 days. day 3 More information needed day 4 day 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts