Question: QUESTION 25 A contractor is doing a FFPC for the government with a budget of 100 million. Current Earned Value data is: EV = 50m;

QUESTION 25

  1. A contractor is doing a FFPC for the government with a budget of 100 million. Current Earned Value data is: EV = 50m; Actual Costs, AC = 75m; and Planned Value, PV=60 m, TCPI: To Complete Performance Index for the project cost is:

    a. 1.25

    b. 0.67

    c. 2

    d. 0.75