Question: QUESTION 25 A contractor is doing a FFPC for the government with a budget of 100 million. Current Earned Value data is: EV = 50m;
QUESTION 25
-
A contractor is doing a FFPC for the government with a budget of 100 million. Current Earned Value data is: EV = 50m; Actual Costs, AC = 75m; and Planned Value, PV=60 m, TCPI: To Complete Performance Index for the project cost is:
a. 1.25
b. 0.67
c. 2
d. 0.75