Question: Question 3 1 6 pointsl ABC has a different WACC for each of the following three risk levels of projects. Low - risk projects have

Question 316 pointsl
ABC has a different WACC for each of the following three risk levels of projects. Low-risk projects have a WACC of 8%, average-risk projects a WACC of 10%, and high-risk projects a WACC of 12%.
a) Which of the following project(s) do you recommend that ABC accept if there is no capital constraint? Explain your answer.
b) Which of the following project(s) do you recommend that ABC aocept if there is a budget of $1 million? Explain your answer.
\table[[Project,Initial Outlay,Level of Risk,IRR],[A,150,000,Low,9.50%
Question 3 1 6 pointsl ABC has a different WACC

Step by Step Solution

There are 3 Steps involved in it