A process consists of three sequential tasks: A, B, and C. The cycle times for individual tasks are given as follows:
Task A: 2min
Task B: 3min
Task C: 5min
Which of the following statements is TRE about this process?
Task A is the bottleneck task.
The throughput rate of the overall process is 12 units/min
Task A is blocked by Task B assuming no buffer space between Tasks A and B.
The process cycle time is 5 mins.