Question: Question #3: (CLO 5) (7 Marks) A project activities and related information are given in the following table. Time Estimates (weeks) Activity Predecessor Optimistic time

Question #3: (CLO 5) (7 Marks) A project

Question #3: (CLO 5) (7 Marks) A project activities and related information are given in the following table. Time Estimates (weeks) Activity Predecessor Optimistic time (a) Most likely time (m) Pessimistic time (b) B 2 4 D F C 2 S 2 2 3 4 D36 D, E 2 Draw a Gantt chart. Draw the AON network and compute the slack for each activity. What is the probability that the project will be completed in 12 weeks or more? 4