Question: QUESTION 3 Table 1 shows activities for a given project with its' precedence and duration. Duration a Table 1: Activity of a project Activity Precedes

QUESTION 3 Table 1 shows activities for a given

QUESTION 3 Table 1 shows activities for a given project with its' precedence and duration. Duration a Table 1: Activity of a project Activity Precedes Start a,b,c, d d f f g b f h h g.1 end end e e 5 6 2 5 9 4 6 3 1 1 (a) Draw the A-O-A network diagram. (10 Marks) (b) Identify the critical path. (5 Marks) (c) Determine expected project duration