Question: Question 3 The criticality index represents the probability that a path is critical the probability that an activity is on the critical path o the

Question 3 The criticality index represents the
Question 3 The criticality index represents the probability that a path is critical the probability that an activity is on the critical path o the correlation index between an activity and the project duration o the probability that a resource is a bottleneck