Question: QUESTION 3 The table below represents a project being analyzed by the critical path method. Activity Duration Predecessor(s) A 5 - B 2 A C
QUESTION 3
-
The table below represents a project being analyzed by the critical path method.
Activity
Duration
Predecessor(s)
A
5
-
B
2
A
C
12
A
D
3
-
E
5
B
F
1
D
G
7
B
H
2
C, E
I
10
F, G
J
6
H, I
What is the critical path?
What is the length of the critical path?