Question: QUESTION 3 The table below represents a project being analyzed by the critical path method. Activity Duration Predecessor(s) A 5 - B 2 A C

QUESTION 3

  1. The table below represents a project being analyzed by the critical path method.

    Activity

    Duration

    Predecessor(s)

    A

    5

    -

    B

    2

    A

    C

    12

    A

    D

    3

    -

    E

    5

    B

    F

    1

    D

    G

    7

    B

    H

    2

    C, E

    I

    10

    F, G

    J

    6

    H, I

    What is the critical path?

    What is the length of the critical path?