Question: Question 32 1.76 pts Your capstone team is deciding how much equipment is needed for a new facility. Based upon your research, you determine that

Question 32 1.76 pts Your capstone team is
Question 32 1.76 pts Your capstone team is deciding how much equipment is needed for a new facility. Based upon your research, you determine that an operation works one 7.5 hour shift, 260 days a year, and has these figures for usage of a machine that is currently being considered. Determine the number of machines that will be required to satisfy capacity Standard Processing Product Demand Time Per Unit (hr) A 250 5 B 2,000 6 30 3 Processing Time Needed (hr) 1250 12000 90 25 4 1 PREVIOUS NEXT