Question: QUESTION 36 Activity Initial Node Final Node Estimated Time A 1 2 2 B 1 3 5 C 2 3 3 D 2 4 4

QUESTION 36

Activity Initial Node Final Node Estimated Time
A 1 2 2
B 1 3 5
C 2 3 3
D 2 4 4
E 3 4 12

Figure 1. Network diagram data for a small project

Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.

1. How many paths does this network diagram have?

5
2
3
4

How long is the critical path?

17
6
15
19

What is the critical path for this project?

A-D
A-C-E
B-E
A-B-E

What is the shortest possible time it will take to complete this project?

6
17
5
15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!