Question: Draw the network and identify the critical path. Job Activity Initial Node Final Node Estimated Time A 1 2 2 B 1 3 3 C
Draw the network and identify the critical path.
Job Activity | Initial Node | Final Node | Estimated Time |
A | 1 | 2 | 2 |
B | 1 | 3 | 3 |
C | 1 | 4 | 3 |
D | 2 | 5 | 3 |
E | 2 | 9 | 3 |
F | 3 | 5 | 1 |
G | 3 | 6 | 2 |
H | 3 | 7 | 3 |
I | 4 | 7 | 5 |
J | 4 | 8 | 3 |
K | 5 | 6 | 3 |
L | 6 | 9 | 4 |
M | 7 | 9 | 4 |
N | 8 | 9 | 3 |
O | 9 | 10 | 2 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
