Question: Draw the network and identify the critical path. Job Activity Initial Node Final Node Estimated Time A 1 2 2 B 1 3 3 C
Draw the network and identify the critical path.
| Job Activity | Initial Node | Final Node | Estimated Time |
| A | 1 | 2 | 2 |
| B | 1 | 3 | 3 |
| C | 1 | 4 | 3 |
| D | 2 | 5 | 3 |
| E | 2 | 9 | 3 |
| F | 3 | 5 | 1 |
| G | 3 | 6 | 2 |
| H | 3 | 7 | 3 |
| I | 4 | 7 | 5 |
| J | 4 | 8 | 3 |
| K | 5 | 6 | 3 |
| L | 6 | 9 | 4 |
| M | 7 | 9 | 4 |
| N | 8 | 9 | 3 |
| O | 9 | 10 | 2 |