Question: QUESTION 37 Consider the following work breakdown structure: Activity B Start Node 1 1 2. 2 3 4 5 6 Finish Node 2 3 4

QUESTION 37 Consider the following work breakdown
QUESTION 37 Consider the following work breakdown structure: Activity B Start Node 1 1 2. 2 3 4 5 6 Finish Node 2 3 4 5 5 6 6 7. Duration Estimate (Days) Optimistic Most Likely Pessimistic 9 15 21 13 21 23 6 9 18 23 35 47 19 27 23 29 41 14 20 2 5 8 26 E F G H 26 What are the estimated slack times (in weeks) for activities A-H? O 1:5; 0; 3: 10; 0; 0; 3; 2 O 10; 0; 1; 5; 0;5; 0; 10 O 5; 1:5; 0; 15;5; 3; 0 O 0;5; 15; 0; 5; 15; 0; 0