Question: Question 4 5 pts Two processes are both capable of making a product. Process A has setup time of 100 minutes and run time of

Question 4 5 pts Two processes are both capable

Question 4 5 pts Two processes are both capable of making a product. Process A has setup time of 100 minutes and run time of 30 seconds per unit. Process B has setup time of 200 minutes and run time of 18 seconds per unit. You would use Process B for volumes greater than or equal to: O 200 units 500 units 220 units 245 units