Question: Question 4 Information on a project is given in the Table below. You are required to: Develop the project activity network using AOA approach? Calculate

Question 4 Information on a project is given in

Question 4 Information on a project is given in the Table below. You are required to: Develop the project activity network using AOA approach? Calculate project time? Activity Preceding activity Activity time (Week) 2 1 Labor-force (persons/week) 6 8 A B C 3 2 D E F G H None None None A BD BD E C.F. G 4 5 12 35 50 60 20 10 6 1