Question: Question 4 - Material Requirements Planning ( 1 0 marks ) A manufacturing company produces product A that comprises of a number of components as

Question 4- Material Requirements Planning (10 marks)
A manufacturing company produces product A that comprises of a number of components as follows. Each unit of product A requires two units of component B and one unit of component C. Each unit of component B requires two units of component D and two units of component E. Each unit of component C requires three units of component B , three units of component D and three units of component E . Each unit of component D requires two units of component F . Finally, each unit of component E requires one unit of component F .
The lead time for items C, D, and F is one week, for items A and B it is two weeks, and for component E it is three weeks.
Lot-for-lot (L4L) production quantity is applied for items C, while the lot sizes for producing items A, B, D, E, and F are in multiples of (25,50,75,60) and 100 units, respectively.
The amount of beginning inventory on hand for components A, B, C, D, E , and F are 10,5,10,70,20 and 70 units, respectively.
There are two scheduled receipts from the company's suppliers: 40 units of component E on Week 5 and 80 units of component F in Week 3.
The customer places an order for product A of 15 units to be delivered in Week 10 and 25 units to be delivered in Week 12.
Based on the above information, answer the following questions:
a. Draw the low-level coded Bill of Material for product A (1 mark)
b. Construct the complete MRP schedule for the above customer order to determine the planned order releases for all items. Can the company fulfill the customer's orders? (3 marks)
c. Construct another MRP schedule based on the original scenario with the following changes on items E and F:
- Both items E and F must have no projected available balance of inventory in Week 12.
- The company has a limited production capacity of 120 units of item E and 300 units of item F per week.
- The company is allowed to purchase items E and F at the maximum of 100 units with schedule receipts in Week 5 and Week 3 respectively.
You just need to show the revised MRP schedule for items E and F based on your MRP schedule in sub-question b). Can the company fulfill the customer's orders? Explain clearly the iteration / steps you take in constructing the MRP schedule for those two items (3 marks)
d. Construct another complete MRP schedule based on the original scenario to determine the planned order releases for all items without any on-hand inventory and scheduled receipt for all items. Can the company fulfill the customer's order?
 Question 4- Material Requirements Planning (10 marks) A manufacturing company produces

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!