Question: QUESTION 40 Consider the following work breakdown structure: Normal Time (wks) Crashing Cost (1 week) (2ad week) 8 5 6 Activity Start B D E

QUESTION 40 Consider the following work breakdown
QUESTION 40 Consider the following work breakdown structure: Normal Time (wks) Crashing Cost (1" week) (2ad week) 8 5 6 Activity Start B D E F G H I Precedes AB CD G E F H H 1 End End aan oo aaa. 6 8 7 3 12 5 6 8 10 5 15 What is the total cost of reducing the project to 18 weeks? (Enter the answer in thousand, i.e., 1 stands for $1,000)