Question: QUESTION 40 Consider the following work breakdown structure: Normal Crashing Time (wks Cost (1st week) (20d week) Activity Start A B 6 4 4 8

QUESTION 40 Consider the following work breakdown

QUESTION 40 Consider the following work breakdown structure: Normal Crashing Time (wks Cost (1st week) (20d week) Activity Start A B 6 4 4 8 5 6 - Precedes AB C.D G E F H H I End End E 5 6 6 6 8 7 3 12 5 6 8 10 5 15 G H I 5 6 - What is the total cost of reducing the project to 18 weeks? (Enter the answer in thousand, i.e., 1 stands for $1,000) h O Cu