Question: Consider the following work breakdown structure: Normal Crashing Time (wks) Cost (1 week) (2nd week) Activity Start B Precedes A, B. CD 6 8 5

Consider the following work breakdown structure: Normal Crashing Time (wks) Cost (1 week) (2nd week) Activity Start B Precedes A, B. CD 6 8 5 6 ADALOM E F G H E F H H I End End 4 5 6 6 8 5 6 7 3 12 5 6 8 10 5 15 V What is the total cost of reducing the project to 18 weeks? (Enter the answer in thousand, i.e., 1 stands for $1,000)