Question: Question 42 The project baseline is established by combining data from the: Work breakdown structure and the project budget. Time-phased project budget and the PERT
Question 42
The project baseline is established by combining data from the:
| Work breakdown structure and the project budget. | ||
| Time-phased project budget and the PERT chart. | ||
| Time-phased project budget and the work breakdown structure. | ||
| S-curve and the project budget. |