Question: Question 5 (35 points). Consider the following data for a project to install a new server at the Northland Pines High School: a) Draw the

Question 5 (35 points). Consider the following data for a project to install a new server at the Northland Pines High School: a) Draw the network diagram. (5 points) b) Calculate the critical path for this project showing all the earliest start, latest start, earliest finish and latest finish times for each activity. ( 25 points) c) How much slack is in each activity? (5 points)