Question: QUESTION 5/ You are installing ten ERP systems modules. . Budget - $100,000 ($10K per ERP Module) . Time - 10 weeks (1 ERP module


QUESTION 5/ You are installing ten ERP systems modules. . Budget - $100,000 ($10K per ERP Module) . Time - 10 weeks (1 ERP module installation per week) You want to check the project performance and at week 5: 4 ERP modules are installed . $47.500 spent to date What is the schedule performance index (SPI)