Question: You are installing ten ERP systems modules. Budget - $100,000 ($10K per ERP Module) . Time - 10 weeks (1 ERP module installation per week)

 You are installing ten ERP systems modules. Budget - $100,000 ($10K

You are installing ten ERP systems modules. Budget - $100,000 ($10K per ERP Module) . Time - 10 weeks (1 ERP module installation per week) You want to check the project performance and at week 5: . 4 ERP modules are installed . $47.500 spent to date What is your analysis and interpretation of the project? under budget and within time Underbudget and overtime )Overbudget and overtime Overbudget and within time