Question: You are installing ten ERP systems modules. Budget - $100,000 ($10K per ERP Module) Time 10 weeks (1 ERP module installation per week) You want
You are installing ten ERP systems modules. Budget - $100,000 ($10K per ERP Module) Time 10 weeks (1 ERP module installation per week)
You want to check the project performance and at week 5: 4 ERP modules are installed $47,500 spent to date
a) What is the cost performance index (CPI)?
b) What is the schedule performance index (SPI)?
c) What would be estimated cost of completing ERP implementation?
d) What would be the estimated time to complete the project in weeks?
e) What is your analysis and interpretation of the project?
_Group of answer choices_
1. Overbudget and within time
2. Underbudget and overtime
3. Overbudget and overtime
4. under budget and within time
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts