You're going to set up ten ERP framework modules.
$100,000 in the budget Each ERP module costs $10,000.
Duration: 10 weeks (1 ERP module installation per week)
You want to evaluate the project's progress, and in week 5:
Four ERP modules have been mounted.
To date, $47,500 has been invested
a) How can you describe your project's study and interpretation?
Under target and on schedule
Extra pay and under budget
Overspending and doing overtime
under target and on schedule
b) In weeks, how long do you think the project would take to complete?
c)How much does it cost to complete Implementation process?
d) What is the CPI, or cost efficiency index?
e)How do you calculate the Plan Performance Index