Question: Question 6 (45 points). Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time

Question 6 (45 points). Consider the following data for a project to install a new server at the Northland Pines High School:

Activity

Activity Time (days)

Immediate Predecessor(s)

A

2

-

B

4

A

C

5

A

D

2

B

E

1

B

F

8

B, C

G

3

D, E

H

5

F

I

4

F

J

7

G, H, I

  1. Draw the network diagram.
  2. Calculate the critical path for this project.
  3. How much slack is in each activity?