Question: Question 6 (45 points). Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time
Question 6 (45 points). Consider the following data for a project to install a new server at the Northland Pines High School:
| Activity | Activity Time (days) | Immediate Predecessor(s) |
| A | 2 | - |
| B | 4 | A |
| C | 5 | A |
| D | 2 | B |
| E | 1 | B |
| F | 8 | B, C |
| G | 3 | D, E |
| H | 5 | F |
| I | 4 | F |
| J | 7 | G, H, I |
- Draw the network diagram.
- Calculate the critical path for this project.
- How much slack is in each activity?