Question: Question 6 The following data was collected for a project: A. Calculate the scheduled completion time and identify the critical path. (5 Points) B. What

Question 6 The following data was collected for a project: A. Calculate the scheduled completion time and identify the critical path. (5 Points) B. What is the slack time for tasks B, C, and D? (5 points) Task Duration Predecessors A 6 None B 12 None 8 A 4 A [TJ 6 B 4 C, G 8 D, E H DE 10 D, E