Question: Activity Duration Predecessors A 3 Weeks - - - B 6 Weeks A C 3 Weeks A D 2 Weeks B E 2 Weeks C
|
Activity Duration Predecessors A 3 Weeks - - - B 6 Weeks A C 3 Weeks A D 2 Weeks B E 2 Weeks C F 2 Weeks D G 2 Weeks E H 4 Weeks D I 1 Week F, G J 5 Weeks E K 3 Weeks H a. Construct a Schedule Network Diagram for the project b. Calculate the scheduled completion time and identify the critical path. c. What is the slack time (float) for activities A, E, F and I? d. What is the slack time (float) for the Path A-C-E-G-I |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
