Question: Question 7 0/1 point The construction site has a task schedule as shown in the table below has a fixed cost of $100 per day,

Question 7 0/1 point The construction site has a

Question 7 0/1 point The construction site has a task schedule as shown in the table below has a fixed cost of $100 per day, but money can be saved by shortening the project duration. Find the least-cost schedule. Activity Normal Time Crash Time 1-2 2-3 1-3 | 2-4 3-4 Cost Increase (1st 2nd, 3rd day) $30, 50, 70 40, 45, 65 60, 60 35, 60 11 $1900 $1750 $1690 $1650 None of the above