Question: Question 7 (1 point) You are considering 2 mutually exclusive risky projects, A and B. Project A has an IRR of 10% and a cost

Question 7 (1 point) You are considering 2 mutually exclusive risky projects, A and B. Project A has an IRR of 10% and a cost of capital of 6%. Project B has an IRR of 9% and a cost of capital of 6%. Project A has an NPV of 10M. Project B has an NPV of 12M. Which of the projects should you select? Project B O Project A You are indifferent between Projects A and B Not enough information to determine which project is preferred