Question: Question 7 The expected time for a project is 20 months with a variance of 4. What is the probability the project will complete within

Question 7 The expected time for a project is 20

Question 7 The expected time for a project is 20 months with a variance of 4. What is the probability the project will complete within 17 months? Not yet answered Select one: Points out of O a. 0.93319 1.00 O b. 0.77337 P Flag question c. 0.22663 O d. 0.06681 e. None of the other options