Question: The expected time for a project is 20 months with a variance of 4. What is the probability the project will complete within 17 months?

The expected time for a project is 20 months with

The expected time for a project is 20 months with a variance of 4. What is the probability the project will complete within 17 months? Select one: O a. 0.77337 O b. 0.93319 O c. 0.06681 O d. None of the other options. O e. 0.22663 Check