Question: The expected time for a project is 20 months with a variance of 4. What is the probability the project will take between 19 and

The expected time for a project is 20 months with

The expected time for a project is 20 months with a variance of 4. What is the probability the project will take between 19 and 25 months? Select one: None of the other options. b. 0.59871 sz s 0.99379 c. 0.98778 O d. 0.5925 e. 1.5925 f. 0.01222 Check The expected time for a project is 20 months with a variance of 4. Within how many months is there a 95% probability of completing? Select one: a. 23.3 b. 1.65 c.26.6 d. None of the other options. O e. 21.65788