Question: Question 8 1 pts Process improvement plan, quality metrics, and quality checklists are the outputs of the q , process of project quality management. controlling
Question
pts
Process improvement plan, quality metrics, and quality checklists are the outputs of the process of project quality management.
controlling quality
planning quality management
quality certification
performing quality assurance