Question: Question 8 Why crash only activities on the Critical Path? The duration of the activities on the Critical Path determines project length. Activities on the

Question 8 Why crash only activities on the

Question 8 Why crash only activities on the Critical Path? The duration of the activities on the Critical Path determines project length. Activities on the Critical Path are the ones with the highest risk. Activities on the Critical Path should not be crashed. The Critical Path is the shortest path