Question: Question 9 (1 point) Consider the following: i Normal time Crash time Crash Cost Activity Predecessor (weeks) (weeks) per week 100 50 100 150 200

Question 9 (1 point) Consider the following: i

Question 9 (1 point) Consider the following: i Normal time Crash time Crash Cost Activity Predecessor (weeks) (weeks) per week 100 50 100 150 200 Calculate the minimum cost of crashing by 2 weeks. 4 00 u O Your