Question: help Question 8 (1 point) Consider the following: Activity Normal time Crash time Crash Cost Predecessor (weeks) (weeks) per week 6 5 100 B 8

help Question 8 (1 point) Consider the following:

help

Question 8 (1 point) Consider the following: Activity Normal time Crash time Crash Cost Predecessor (weeks) (weeks) per week 6 5 100 B 8 6 50 4 3 100 D 5 3 150 A E 8 5 200 Calculate the minimum cost of crashing by 2 weeks