Question: Question 90 The minimum amount of time a dependent activity must be delayed to begin or end is referred to as: a. Laddering b. Cushion
Question 90
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
a.
Laddering
b.
Cushion
c.
Lag
d.
Hammock
Question 91
In a resource-constrained project the third priority in assigning resources is usually given to activities with the:
a.
Smallest duration
b.
Least slack
c.
Most slack
d.
Lowest identification number
Question 92
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true?
a.
We should check to see if all the bills have been paid
b.
We are spending less than we should for the project
c.
We are doing a good job managing the project
d.
We can't be sure how the project is going
Question 93
Which of the following would not be considered a threat?
a.
Economic conditions
b.
International disruptions
c.
Inflation
d.
Meeting the project schedule
Question 94
Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?
a.
CV, SU, and BAC
b.
BAC, EAC, and ETC
c.
PV, EV, and AC
d.
VAC, EAC, and BAC
Question 95
Which of the following is not one of the factors that need to be considered to improve quality of estimates for project times and costs?
a.
Profit
b.
People
c.
Padding estimates
d.
Planning horizon
Question 96
One type of cost and time estimates is mainly based on analogy, group consensus and simple mathematical relationships. This type is:
a.
Learning curves
b.
Function point method
c.
Bottom Up estimates
d.
Top Down estimates
Question 97
In reviewing the status of her project with top management, Shirley was told that there only were two programmers that she could use for her project. Her project is __________ constrained.
a.
Quality
b.
Cost
c.
Resource
d.
Time
Question 98
In a resource-constrained project, the first priority in assigning resources is usually given to activities with the:
a.
Least slack
b.
Most slack
c.
Smallest duration
d.
Lowest identification number
Question 99
Which of the following is not one of the potential responses to a specific risk event?
a.
Mitigating
b.
Transferring
c.
Retaining
d.
Ignoring
Question 100
A typical project progress report would contain all of the following sections except:
a.
Current status of project
b.
Progress since last report
c.
Problems and issues since last report
d.
All of these are typical sections