Question: The minimum amount of time a dependent activity must be delayed to begin or end is referred to as laddering. buffer. hammock. lag. cushion.

The minimum amount of time a dependent activity must be delayed to begin or end is referred to as
laddering.
buffer.
hammock.
lag.
cushion.