Question: The minimum amount of time a dependent activity must be delayed to begin or end is referred to as Question 1 0 options: lag. buffer.
The minimum amount of time a dependent activity must be delayed to begin or end is referred to as
Question options:
lag.
buffer.
cushion.
laddering.
hammock.