Question: Question a.) Determine the probability that the project completion time will exceed 35 days. b.) Also, determine the probability of the project being completed in

Question
a.) Determine the probability that the project completion time will exceed 35 days.
b.) Also, determine the probability of the project being completed in less than 30 days.
7. Use the table below for the following problem. 5 points) Time Estimates days) Pred a m Activity 1 O 4 8 2 0 b 12 15 14 13 6 2 1 10 10 3 0 4 1 5 1 6 9 6 12 3 18 3 7 8 3,5,6 9 15 22 a. Determine the probability that the project completion time will exceed 35 days. b. Also determine the probability of the project being completed in less than 30 days