Question: Question a.) Determine the probability that the project completion time will exceed 35 days. b.) Also, determine the probability of the project being completed in

Question a.) Determine the probability that the

Question

a.) Determine the probability that the project completion time will exceed 35 days.

b.) Also, determine the probability of the project being completed in less than 30 days.

7. Use the table below for the following problem. 5 points) Time Estimates days) Pred a m Activity 1 O 4 8 2 0 b 12 15 14 13 6 2 1 10 10 3 0 4 1 5 1 6 9 6 12 3 18 3 7 8 3,5,6 9 15 22 a. Determine the probability that the project completion time will exceed 35 days. b. Also determine the probability of the project being completed in less than 30 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!