Question: QUESTION ANSWER 8 Lead time for computers is 7 days with daily demand of 5 computers and a C) safety stock of 1 day. Each
QUESTION ANSWER 8 Lead time for computers is 7 days with daily demand of 5 computers and a C) safety stock of 1 day. Each kanban holds 8 computers. What is the correct number of kanbans? C) 5 C) | DON'T KNOW YET